Electricity update- Canouan 75% complete, poles deployed to Union Island
An update of the restoration work in the Southern Grenadines was provided by the St Vincent and the Electricity Services Ltd. outlining progress made so far since the passage of Hurricane Beryl.
The following are updates for each island, as of August 11, 2024.
Canouan
Restoration of the primary and secondary distribution network continues in Canouan, with an average of 75 per cent of the work being completed. Remaining work is expected to be complete within the next two weeks. Reconnection of homes and businesses will commence once the Electrical Inspectorate certifies that the electrical wiring of each building is safe to receive power.
Mayreau
Sections of the network were energized on August 5, 2024 and power was restored at the Health Clinic. A VINLEC team, supported by contractors, will continue work to restore the network this week. Again, buildings will be energized when VINLEC receives certificates indicating that it is safe to do so.
Union Island
Over 120 solar street lights have been installed, with an additional 100 planned for installation to further illuminate the island. Poles have been deployed to Union Island to rebuild the primary and secondary distribution network and a containerized generator (that offers some sound attenuation) was taken to the Union Island Power Plant. The initial aim is to provide power to essential services including the Health Centre, the Airport, and the town square.
VINLEC remains committed to restoring power as swiftly and safely as possible. We appreciate the patience and cooperation of all affected residents.