Searchlight Logo
special_image

    • News
      • Front Page
      • News
      • Breaking News
      • Press Release
      • From the Courts
      • Features
      • Special Features
      • Sports
      • Regional / World
      • Regional / World
    • Opinions
      • Editorial
      • Our Readers’ Opinions
      • Bassy – Love Vine
      • Prof. J Robinson – Eye of the Needle
      • Dr. Fraser- Point of View
      • R. Rose – Eye of the Needle
      • On Target
      • Dr Jozelle Miller
      • The World Around Us
      • Random Thoughts
    • Advice
      • Kitchen Corner
      • What’s on Fleek this week
      • Health Wise
      • Physician’s Weekly
      • Business Buzz
      • Hey Rosie!
      • Prime the pump
    • ePaper
    • Obituaries
      • In Memoriam / Acknowledgement
      • Tribute
    • Contact Us
      • Advertise With Us
      • Letters To The Editor
      • General Contact Information
      • Contact our Webmaster
    • About Us
      • Privacy Policy
      • Interactive Media Ltd
      • St. Vincent & the Grenadines
    • Subscribe
    • News
      • Front Page
      • News
      • Breaking News
      • Press Release
      • From the Courts
      • Features
      • Special Features
      • Sports
      • Regional / World
      • Regional / World
    • Opinions
      • Editorial
      • Our Readers’ Opinions
      • Bassy – Love Vine
      • Prof. J Robinson – Eye of the Needle
      • Dr. Fraser- Point of View
      • R. Rose – Eye of the Needle
      • On Target
      • Dr Jozelle Miller
      • The World Around Us
      • Random Thoughts
    • Advice
      • Kitchen Corner
      • What’s on Fleek this week
      • Health Wise
      • Physician’s Weekly
      • Business Buzz
      • Hey Rosie!
      • Prime the pump
    • ePaper
    • Obituaries
      • In Memoriam / Acknowledgement
      • Tribute
    • Contact Us
      • Advertise With Us
      • Letters To The Editor
      • General Contact Information
      • Contact our Webmaster
    • About Us
      • Privacy Policy
      • Interactive Media Ltd
      • St. Vincent & the Grenadines
    • Subscribe
ARNOS VALE CRICKET GROUND RUNNING BEHIND SCHEDULE
Front Page
November 10, 2006

ARNOS VALE CRICKET GROUND RUNNING BEHIND SCHEDULE

The Local Organising Committee (LOC) for Cricket World Cup 2006 has 51 days in which to complete the $30 million makeover of the Arnos Vale facility and there are questions about whether they can make the deadline.

The answer is “yes and no”.

On December 31 when it hands over the property to the International Cricket Council (ICC) the double-decker stand will not be finished and that’s because it’s not a priority, said an LOC official.{{more}}

The LOC Construction Consultant Deirdre Myers told SEARCHLIGHT that as far as ICC was concerned the priority items were the media centre, players pavilion, and the pitches and the outfield.

With this understanding, she was confident that St Vincent and the Grenadines will get a favourable response from officials of the ICC when they visit November 24.

“We are shooting for handing over to the Cricket

World Cup Committee for the end of the year, this includes buildings, external works, fencing, basically the entire park,” Myers projected.

She disclosed that completion of the double-decker stand, which has holding capacity of 5,300 spectators, has been rescheduled to the end of January from its initial December 1 deadline.

Myers said that facility is not high on the priority list of the ICC. Myers however, has the completion of the Media Centre as her major focus of attention.

“It is the most complex of all buildings, not by design but by provisions, as it houses the written, radio and television press” Myers advanced.

The Construction Consultant said that there are measures in place in the event of any unforeseen circumstances.

“From my meetings with the various contractors we have looked at ways of increasing staff. They have done so in quite a few cases, worked on weekends and extended the working hours”, Myers admitted.

Project Manager Charlie Crichton, of Gibson Construction, the firm contracted to deliver the double-decker and media centre was terse in his comments.

“We will finish in time,” Crichton said.

St Vincent and the Grenadines will host Australia, England, Zimbabwe, and Bermuda in official warm up matches in March next year ahead of the group stages of Cricket World Cup.

An upgrade of the main Arnos Vale playing Field, the Sion Hill Playing Field and the Stubbs Playing Field began last year.

The latter fields that will be used as practice venues have undergone substantive renovations, with the re-grassing of the out fields and the erection of better players’ quarters.

Arnos Vale, the showpiece venue has taken the major chunk of the refurbishing with a reconfiguration of the facility and the realignment of the Arnos Vale River.

  • FacebookComments
  • ALSO IN THE NEWS
    Gov’t investigating operations of statutory corporations under ULP
    Front Page
    Gov’t investigating operations of statutory corporations under ULP
    Webmaster 
    September 22, 2026
    THE GOVERNMENT said it has discovered discrepancies in some statutory organisations that need deeper investigation with the possibility of holding peo...
    ‘Wiped Computer’ matter still under investigation – Foreign Affairs Minister
    Front Page
    ‘Wiped Computer’ matter still under investigation – Foreign Affairs Minister
    Webmaster 
    September 22, 2026
    THE CLAIM that the computers at the St Vincent and the Grenadines (SVG) Consulate in NewYork (NY) were wiped is still being investigated by the New De...
    SVG has no capacity for borrowing says PM Friday
    Front Page
    SVG has no capacity for borrowing says PM Friday
    Webmaster 
    September 22, 2026
    THE GOVERNMENT of St Vincent and the Grenadines (SVG) can no longer borrow and invest. “...there is no room for it...”, Prime Minister Dr. Godwin Frid...
    Cuba as national security threat to US ‘entirely farcical’, says Gonsalves
    Front Page
    Cuba as national security threat to US ‘entirely farcical’, says Gonsalves
    Webmaster 
    September 22, 2026
    ST VINCENT AND THE Grenadines’ Opposition Leader, Dr. Ralph Gonsalves has characterized Washington’s framing of Cuba as a national security threat as ...
    SSU conducts basic security course for 16 Auxiliary Recruits
    Front Page
    SSU conducts basic security course for 16 Auxiliary Recruits
    Webmaster 
    September 22, 2026
    Sixteen Auxiliary Police recruits have begun three weeks of intensive training under the Special Service Unit’s Basic Security Course No. 1 of 2026, a...
    SVG listed in six categories for recognition in Wanderlust Reader Travel Awards
    News
    SVG listed in six categories for recognition in Wanderlust Reader Travel Awards
    Webmaster 
    September 22, 2026
    ST.VINCENT AND THE Grenadines (SVG), has been shortlisted in six categories in the 2026 Wanderlust Reader Travel Awards, one of the United Kingdom’s l...
    News
    SVG listed in six categories for recognition in Wanderlust Reader Travel Awards
    News
    SVG listed in six categories for recognition in Wanderlust Reader Travel Awards
    Webmaster 
    September 22, 2026
    ST.VINCENT AND THE Grenadines (SVG), has been shortlisted in six categories in the 2026 Wanderlust Reader Travel Awards, one of the United Kingdom’s l...
    SVG recommits to more awareness and early diagnosis to mark World Alzheimer’s Day
    News
    SVG recommits to more awareness and early diagnosis to mark World Alzheimer’s Day
    Webmaster 
    September 22, 2026
    ST.VINCENT AND THE Grenadines joined communities around the world in observing World Alzheimer’s Day 2026 with renewed emphasis on the importance of e...
    Canouan chef fined for possession of marijuana
    From the Courts, News
    Canouan chef fined for possession of marijuana
    Webmaster 
    September 22, 2026
    A chef of Canouan was ordered to pay over EC$ 1,000 when he appeared in court on September 21, 2026 on two marijuana charges. Twenty-two-year old Jova...
    PM Friday discusses Climate Resilience issues with UN Secretary-General
    News
    PM Friday discusses Climate Resilience issues with UN Secretary-General
    Webmaster 
    September 22, 2026
    PRIME MINISTER Dr. Godwin Friday met on Sunday, September 20, 2026 with United Nations Secretary-General António Guterres, at United Nations Headquart...
    Agreement signed to help farmers market produce using digital technology
    News
    Agreement signed to help farmers market produce using digital technology
    Webmaster 
    September 18, 2026
    The Government of St Vincent and the Grenadines (SVG), is advancing a data-driven partnership to connect local farmers to international buyers while d...

    E-EDITION
    ePaper
    google_play
    app_store
    Subscribe Now
    • Interactive Media Ltd. • P.O. Box 152 • Kingstown • St. Vincent and the Grenadines • Phone: 784-456-1558 © Copyright Interactive Media Ltd.. All rights reserved.
    We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.Ok